Moving Hobart Goods Shed for Macquarie Point stadium to cost $6.5 million

Picture of Pulse Tasmania
The Goods Shed will be moved to sit alongside the proposed Macquarie Point stadium. Image / MPDC

The relocation of a heritage-listed railway shed to make way for Hobart’s proposed Macquarie Point stadium will cost more than $6 million, new documents show.

The circa-1915 Hobart Goods Shed currently sits in the middle of the planned $775 million multi-purpose stadium site.

Advertisement

It is set to be moved to the north-west gate area of the waterfront precinct.

Documents submitted to the Tasmanian Planning Commission (TPC) by the Macquarie Point Development Corporation (MPDC) estimated relocation to cost $6.5 million.

The 1915 Hobart Goods Shed has been listed on Tasmanian heritage register. Image / Goods Shed

The figure was one of several to be recently requested by the TPC as it continues to assess the stadium as a Project of State Significance (POSS).

“After we submitted our POSS application in September, the TPC wrote to us late last year asking for more detail on some aspects of the project,” an MPDC spokesperson said.

The historic goods shed was built at Macquarie Point in Hobart in 1915. Image / Tasmanian Archives and Heritage Office

“Seeking clarifications and further information is a normal part of assessing large and complex developments.”

The latest budget figures show the total cost of the stadium itself is projected to be $774.9 million.

Advertisement

Costings for key components of the planned stadium:

Component Cost
Main Roof $207,080,593
Upper Floors – Tiers $70,171,368
Facade $68,638,286
Market Loading – Non Local Trades (Roof, Facade, Finishes and Services) $62,265,660
Upper Floors – Flat Slabs (incl Stair) $49,094,808
Electrical & ICT Services $33,658,843
Foundations $32,895,753
Mechanical Services $26,437,068
Bulk Excavation/Contaminated Material $25,564,162
Hydraulics $20,718,307
Internal Walls and Doors $17,798,093
Fitments and Equipment $15,481,934
Structural Walls $12,770,368
Columns $11,496,827
Lower Roofs $10,929,681
Fire Services $10,052,377
Sports Lighting $9,022,825
Floor Finishes $8,954,157
Ground Slabs $8,343,207
Stadium Seating $7,868,854
ESD – Concrete / Timber / Rain / Solar $7,672,327
Signage / Theming $7,503,192
Ceilings $6,967,825
Field of Play $6,857,879
Landscaping & Civil Works $6,674,991
Wall Finishes $6,105,641
Lifts $5,755,613
Facade – Pitch Side $5,253,754
Stadium Special Equipment $3,989,039
BWIC for Services $3,093,560
Main Comms & Racks $2,849,313
Cricket Wickets $1,424,657
Demolition $1,134,131
AFL Technology $189,954
Cricket Australia Technology $189,954
Total $774,905,001

More of The Latest

News

Advertisement
Advertisement

Share this article

Facebook
WhatsApp
Twitter
Email
Print