Independent MP Peter George has tabled a bill that would halt new data centre permits until planning rules and a state water and energy policy are in place.
Under his Data Centre Safeguards Bill 2026, data centres could not be declared major projects during the moratorium and any declared a project of state significance would need final approval from both houses of parliament.
George said he wanted the planning rules to keep data centres out of residential and light industrial areas and off prime agricultural land.
“It’s not anti-data centres. It’s not for data centres. It’s not anti-jobs,” he said.
“It simply sets the basic ground rules for the industry.”

Premier Jeremy Rockliff told parliament in question time on Tuesday the government would not support moves “around moratoriums, legislation and the like”.
Under the bill, pending applications would be assessed under existing rules, but permit extensions would be blocked, so developers would have to start work within their original timeframes.
The moratorium would lift once the planning rules and state policy were in place and the act would expire by the end of 2037.
The government’s expectations, released on Friday, require developers of facilities larger than 20 megawatts to pay at least $3,000 a year per megawatt into a local community benefit fund and report their energy and water use quarterly.
They are not legislated and will be reviewed after six months.

George said his bill would underpin the expectations with legislation “rather than making it a thought bubble”.
He said it was not intended to stop proposals already underway, including Firmus’ three planned sites.
He said the bill could be debated next week and needed to be considered “pretty urgently”.
George’s self-managed super fund holds shares in Goodman Group, a property developer whose development pipeline is 78% data centres, according to its latest annual results.

George said he bought the shares in the past 12 months and saw “absolutely no conflict at all”.
“I will of course keep an eye on what Goodman does, because if I don’t approve of what it does I’ll sell it, just like I’d sell other shares,” he said.
Labor leader Josh Willie yesterday asked Rockliff to commit to Labor’s rule that data centres not connect to the grid until new generation was locked in, but he did not.
Rockliff said claims power bills would rise were “a falsehood” and that data centres would pay “top dollar” for power, benefiting Hydro Tasmania.
Asked to publish a list of proposals, Rockliff instead said he had been advised Firmus was the only company with a grid connection application.

He accused Labor of offering “a blank sheet of paper” on data centres.
Speaking after question time, Willie said Rockliff had “rolled out the red carpet for data centre developers”.
“Data centres done in the best interests of Tasmania are a good thing, but nobody trusts Premier Rockliff to negotiate a good deal for Tasmania,” he said.
On Sunday, Labor called for no new data centres or agreements until stronger safeguards were in place.
The Greens, who back a moratorium, say Labor voted with the government against one in September.

More than 10,000 people signed a parliamentary petition, tabled in September, calling for a moratorium on unfinished AI data centres.
Hydro Tasmania has told a parliamentary inquiry Firmus has proposed about 444 megawatts across its three sites, which would make it the state’s largest electricity user.