The estimated cost of the Macquarie Point stadium has risen by $100 million to $1.23 billion.
Premier Jeremy Rockliff released the figure this morning, saying the final cost could still change while the last stage of procurement continues.
The previous estimate of $1.13 billion was set in November 2025.
Treasurer Eric Abetz told a press conference that contingency had been left out of the new figure.

“The figures that have been announced today by the premier do not include contingencies and of course that’s for very obvious commercial reasons that they are not disclosed,” he said.
“In relation to the funding of the project, any shortfall will have a funding facility made available to enable the project to be completed.”

Rockliff also gave the cost of works across the broader Macquarie Point precinct, including a centralised car park and power and water upgrades, as $132 million.
He said project delivery costs, including all costs managed by the Macquarie Point Development Corporation, were $183 million.
“We’ll see those costs begin to be recouped as private investment is locked in across the precinct,” Rockliff wrote on social media.
He blamed the cost increase on conflict in the Middle East.

“With war in Iran, costs have changed – that’s the reality we’re all living in,” he said.
The update follows an upper house motion calling for the cost to be revealed before the contract is signed.
The premier promised last week to release the figures before parliament breaks for the year.
More to come…