A state government department has asked the West Coast Council to refund about $30,000 in planning fees for its Next Iconic Walk project, citing rising costs.
Council staff have recommended councillors reject the request.
The Department of Natural Resources and Environment Tasmania paid a $64,692.13 fee when it lodged the development application in October and is seeking a 50% rebate.
Council fees for development applications are calculated as a percentage of the total project cost.

In a letter to the council, department secretary Jason Jacobi said rising transport and material costs, including the impact of conflict in the Middle East, meant the project team was “continually looking for cost savings and efficiencies to keep the project within the $40 million budget allocation”.
He said the walk had been through a multi-year environmental assessment, which reduced the amount of assessment needed from the council.

He said the project would create an “estimated 139 jobs during construction and 40 jobs once operational”.
“The project team are looking for every opportunity to maximise the output of the project to deliver its full potential, which includes dedicating as much of the project budget to support West Coast businesses and provide infrastructure for locals and visitors to use,” he wrote.
The three-day, two-night walk would cover 31 kilometres between Lake Plimsoll and Lake Margaret Power Station, in the Tyndall Range between Queenstown and Tullah.
According to a council report, Parks and Wildlife staff raised a fee reduction before lodging the application.

They were told only councillors could decide and could not do so while the council was in caretaker mode ahead of the local government elections.
The council’s director of community and corporate services said the department’s points were “valid”, but the project had already taken up “considerable” time from council staff and councillors.
The report said that in the context of the project’s total budget, “any rebate council was to offer would be considered negligible in terms of the bottom line”.
“The project will proceed regardless of whether council offers a rebate,” the report states.

Council planning approval is the last major approval the walk needs.
The federal government decided in April that it did not need further assessment under national environment laws and parliament’s Public Works Committee approved it later that month.
Subject to all approvals and permits, the walk is on track for completion in 2029.
The newly elected council will consider the fee request at its meeting in Queenstown on Tuesday.